11th & 12th May
Final Preparation for Phase 1
Final Preparation for Phase 1
The Calm Before the Storm
Last Nights ‘Work Party’
The Gang has been building dumper crossings for use in the upcoming May possessions
Demolishing a section of wall by Bridge 22 at Haworth
Phase 1 of Bridge 27 Renewal: Complete!
Back in Steam & assisting with the Bridge 27 replacement.
Moving surplus Materials to Oakworth before bringing back 50+ Sleepers.
The last day of the possession was yesterday, with the Railway handed back at 20:30.
As the week draws to a close, we are pleased to say the job ran on time.