15th April
The Pile Mat dug out at the Keighley side of the Bridge while drainage work is carried out on the Oxenhope Side of the Bridge.
The Pile Mat dug out at the Keighley side of the Bridge while drainage work is carried out on the Oxenhope Side of the Bridge.
A Preparation Week, with the main focus being drainage work and then installing the piling mats.
Today has seen the Trench Boxes constructed and ready for the coming week’s possession at Bridge 27.
Yesterday evening saw the first Tuesday Evening working gang of 2024; the small gang split into two groups with work focused on Bridge 27 preparation works.
Over the last few weeks, a small team has been chopping sleepers up to make infills for the siding span of Bridge 27.
Our partners at Cass Hayward have crafted these detailed 3D model images
Today marks the commencement of cable installation through the recently implemented ducts.
This week, we will see another week of preparation work for the Bridge 27 renewal in September.
New opening times for the Railway’s Bar.
Dates for upcoming work and Haworth Station Car Park restrictions.