Bridge 27 PHASE 1
Final Preparation for Phase 1
The work began early, with Keller UK starting piling work on the North Side of the Bridge, while the KWVR Gang began the task of installing the pile mat on the south side of the bridge, which will be piled next week. Work is progressing well, with only a few hiccups resolved quickly.